MECHANICAL
Elevator : 2
passenger elevators, 1 passenger service elevator
Load Capacity : 900
kilos lift capacity (ave. 14-15 persons)
No. of Passengers : Transports average of 43 persons every
5 minutes
Speed : 2.5
sec. floor to floor with 30-32 sec. waiting time only |
FIRE
PROTECTION / ALARM
- Water sprinkler system
- Fire alarm and detection system
Security
- Basic CCTV at Lobby and Elevators |
| II.
Project Finishes
Unit Floor Finish
Living / Dining / Bedrooms
: Tanguile Wood Parquet
Utility Room/Maid's Room/Bedroom
: Local Ceramic Tiles
Unit Wall Finishes
Living / Dining / Bedrooms
: Cement Plastered or Drywall Partition/Painted
Utility Room/Maid's Room
: Plain Cement Plastered, Painted
Toilet and Bath
: Local Ceramic Tiles
Ceiling Finishes
Living / Dining / Bedrooms
: Rubbed Concrete, Painted
Toilet and Bath
: Gypsum Board, Painted
Other Finishes
Glass
: Tinted green, 6mm thick
Cabinets
: All closets and cabinets are modular
Facade Treatment :
Glass with concrete
|